31 May

So far it’s really hard to tell how much behind I’ll end up in a week or so, but I’m working on as planned in the schedule. I know it will require a lot of work to catch up, but so far I’m on the right track. I also still have some time later on included for bugs or errors, that I may use to make some more assets and fix the problems that may appear right now at the beginning. This is my biggest weakness so far, but at this point I’m still not as much stressed as I probably should be. I still have lots of time to catch up, so if I’ll play it right I’ll make everything on time.

Terrible beginning!

If someone would ever told me, that I’ll spend entire two weeks in a bed having a terrible cold during a spring, I would lough so loud, but IT HAPPENED! I had a temperature, barely able to think straight, so I decided that working on a project won’t do me any good. The illness hold to me for two weeks, starting with a bee sting (YES, THAT’S EVEN WORSE!). This again ruined my schedule, but this time I’ve decided not to make any changes to the actual Gantt Chart. I’ll have to live with it and try to catch up with that lose and hope that nothing wrong will happen again during this project…

This means that so far I haven’t even really started the project. I’ll have to work harder that expected for the next few weeks to make everything on time…

Reorganisation of a Schedule

The plan was, to start a little bit early before the beginning of the project, but because last few weeks were so intense, I needed a break so much, that I’ve decided to reorganise my schedule and include two weeks of a break. This an important decision that allowed me to recharge and come back to work with a full power. This also means that I will have two less weeks for the entire project, but I feel strong about it, so it should be fine.

That means, that I had to redo my Gantt Chart to exclude the first two weeks. I wanted to do so, just because I didn’t wanted to write every week that I’m behind the schedule…

The Gantt Chart before:

The Gantt Chart now:

The actual schedule didn’t change as much, but I’ve cut one week of the LAB interior. I decided that it will mostly be copy and paste, so I don’t need as much time do to the assets. I want to focus on the plants and trees a bit more and the to create an appropriate atmosphere on the outside rather than the inside.